Stage 3: to build


After searching through builders, signing off the contract and options, the actual building, to construct the home comes next.

Our contract stipulated 13-14 months to completion, which is Feb/Mar 2022, with 10% down on home plus the lot. The construction begins in October 2021 due to delays (shortages) caused by the covid-19 pandemic:


2021 Oct construction begins
2022 Feb drywall inspection
2022 Sept final walk-through
2022 Sept closing 

The process:

We received our first image of the home on November 4th, 2021 when the walls are already up.

During the construction process, the sales agent should send updates with photos. But ours isn’t responsive, which is the norm. The first update came when one of our neighbors who posted photo of our street in Facebook group. Most photos of our home (below) are from neighbors.

Our timeline

           

The following photos illustrate the process. Photo credits go to many neighbors when they posted on FB.

  1. pave the road, curbs prepare/clear the ground
  2. stake out the lot/forms
  3. rough plumbers
  4. pour the slab
  5. walls: outer wall’s blocks, going upwalls, 4×8 boards
  6. roof, membrane, tiles
  7. inside of the house
  8. Windows
  9. curbs/sidewalk

         

The roofers, Nov 2, 2022. They played the music in the morning. Then, perhaps, went to lunch. Then, all work in the afternoon, without any accompanying sound. A few nights, they worked into dusk, taking advantage of the last ray. This is how they prepare to lay the pavers.